Scope and design calculations will be done after

Scope Statement

Cameco
Corporation’s Eagle Point Mine is an active underground uranium operation
located at the Rabbit Lake mine site in northern Saskatchewan. Eagle Point
Deposit was initially discovered in 1980 by Gulf Minerals Canada Ltd. while
drill testing geophysical and geochemical anomalies northeast along strike from
the Collins Bay Uranium deposits. The Eagle Point deposit is largely under the
bed of Collins Bay. Sublevel open stopping method is used at Eagle Point mine
to extract the uranium. The uranium mined at Eagle Point Mine is processed at
Rabbit Lake Mill. Cameco Corporation is expanding Eagle Point Mine below the
542 level to extract a new ore zone.

We Will Write a Custom Essay Specifically
For You For Only $13.90/page!


order now

I
would like to develop a mining plan to successfully mine the new area as my
capstone project. The purpose of this project is to develop an optimum mining
plan based on the selection of an appropriate mining method to extract a new
ore zone. The following tasks would be included in this project:

·        
A detailed background investigation into the
Rabbit Lake Mine area.

·        
A literature review which included backfill,
mining methods, and required equipment.

·        
A preliminary analysis of mining methods using
the UBC (University of British Columbia) mining method selection and Taylor’s
Rule.

·        
Development of infrastructure tonnage and costs.

·        
Use of AutoCAD/Vulcan software to present the
initial development of the mining plan.

·        
Development infrastructure tonnage and costs.

·        
Mineral reserve estimates for the new mining
zone, including cut-off grade, dilution, and recovery rates.

·        
Develop a production schedule to successfully
mine the new area.

Methodology

The primary step
for this project is to do the literature review based on detailed information
such as the
history of Rabbit Lake Mine, Eagle Point Mine’s current production, orebody
shape, geology, cost analysis, current mining method, equipments available at
site and project constraints. The mining method will be based on the ore-body
geometry and rock mass characteristics. The UBC mining method and Taylor’s Rule
will be used to select the optimum method. The production rates, tonnage, value
of deposit, operating costs, equipment requirement and design calculations will
be done after the selecting mining method. The layout will be designed as per
ore deposit shape, equipment size and any other requirements to complete the
operations. Eventually, a production schedule will be developed to mine the new
ore zone using the Microsoft Project.

Sources
of Information

The
following resources will be required to successfully complete my project:

·        
Internet will be
the primary source of information for this project.

·        
Cameco Corporation
official website: www.cameco.com

·        
Saskatchewan
Polytechnic Library

·        
Textbook:
Introductory Mining Engineering (Hartman, 1961)

·        
Information and
material provided by the instructor

·        
Computer software
such as:

– Designing Software: AutoCAD/Vulcan

– Microsoft Office Suite, including Microsoft Project

Work
Schedule

This project comes under PROJ – 297, which runs from
January to May. So, the proposed work schedule for my project is as follows:

Literature
Review

January-February

Methodology

February-March

Design

March-April

Mining schedule

April

Proof  Reading for Technical Report

May

Poster

May

Presentation

May

 

Risk Register

Identified Risk

Root
Cause

Potential Solution

Scope Creep

·        
Lack of clarity about the project
·        
Lack of foresight and planning
·        
Failure to fully understand the problem
·        
Large number of changes in project scope

·        
Do proper planning and clearly
define requirements of project
·        
Control the growth of scope
·        
Be prepared to defend against excessive
changes
·        
Avoid gold plating ideas in project

Identified Risk

Root
Cause

Potential Solution

Insufficient
resources

·        
Lack of
commitment
·        
Inability to secure
sufficient resources
 

·        
Explore various channels to secure
resources
·        
Consider alternative approaches

Time Management

·        
Study load of
other courses, assignments, exams
·        
Any health
issues can cause delays

·        
Make a proper
time table
·        
Always try to do
other works well in advance
·        
Follow safety
measures to stay fit and to avoid any injury

Design and
Technology

·        
Infeasible
design
·        
Low flexibility
in design
·        
Incorrect
calculations
·        
Poor Quality of
designing software as well as computer

·        
Always do  design reviews
·        
Use proper
methods for calculations and verify them
·        
Fix the problems
regarding technical equipments as soon as possible

Communication

·        
Hesitation in
discussing issues
·        
Misunderstanding
and misinterpretation of requirements
·        
Availability of
required person

·        
Discuss problems
with instructors
·        
Do  weekly or bi-weekly meetings with project
head/instructor
·        
Prior requests
to meet anyone

 

Conclusion

 